Public Service Resources

James Herron
Director of Public Service

Jeffery C. Minch
Assistant Director of Public Service

City of Middleburg Heights
15700 Bagley Road
Middleburg Heights, Ohio 44130

Phone (440) 234-2216

More Resources
2024 ROAD CONSTRUCTION PROJECTS

Work zone, slow down, workers have families that want them around.

UPDATED May 29, 2024

Mayor Matthew J. Castelli and the Middleburg Heights City Council understand that maintaining our roads is a top priority.  The Middleburg Heights Department of Public Service and Director James Herron coordinates and manages the work with our City Engineer – Mackay Engineering, a Wallace Pancher Company and regional partners including Cuyahoga County, the Northeast Ohio Areawide Coordinating Agency (NOACA), and the Ohio Department of Transportation.

Listed below are the planned and funded 2024 Middleburg Heights Road Construction Projects.  This list is updated periodically as projects are approved and funded by Middleburg Heights City Council or our outside partners.

Grant Boulevard (Webster Road to Dead End)
The project involves pavement planing with chip seal and asphalt overlay, concrete curb and section repairs.

Project Update:  Project was awarded to Crossroads Asphalt Recycling, Inc. and work will start in mid-June 2024.

Arrowhead Drive
Arrowhead Drive will receive full depth pavement, curb and driveway apron removal. The street, curb and driveway aprons will be poured with concrete.

Project Update:  Project was awarded by City Council to Tri-Mor Corporation.

Sheldon Road (Engle Road to Smith Road)
Sheldon Road from Engle Road to Smith Road is being repaved starting on or after July 1, 2024. The Cuyahoga County Department of Public Works is bidding and managing the project for the cities of Middleburg Heights and Brook Park.

Project Update:  Cuyahoga County awarded the project to Karvo Paving.  Project is being managed by the Cuyahoga County Department of Public Works and is receiving 80% federal funding through the support of the Northeast Ohio Areawide Coordinating Agency (NOACA).

Smith Road (Pearl Road to W. 130th Street)
Smith Road in the Southland business district is being completely reconfigured and reconstructed.  The reimagined corridor will have on-street parking, a new multi-purpose trail, a tree lined center median, enhanced green space along the entire roadway, and new opportunities for development adjacent to Smith Road.  The project is starting in early Summer 2024 and will be completed by Spring 2026.

Project Update:  Project was awarded by City Council to Perk Company.

Smith Road (Sheldon Road to Pearl Road)
Smith Road is being completely repaved from Sheldon Road to Pearl Road.  The curve located near Stroud Road is being realigned for safer traffic flow and travel.

Project Update:  Project is being bid and managed by the Cuyahoga County Department of Public Works.  A new waterline, storm sewers, and curve realignment work near Stroud Road will occur on Smith Road in Fall 2024. The repaving work on Smith Road will start in Spring 2025.

General Pavement Services Contract

The City of Middleburg Heights awarded the contract to Crossroads Asphalt Recycling, Inc. in Spring 2024.

Ragall Parkway
Crossroads Asphalt Recycling, Inc. is repaving the entire length of Ragall Parkway.

Fowles Road
Fowles Road will have section repairs and be cracked sealed in Summer 2024.