2023 ROAD CONSTRUCTION PROJECTS

Work zone, slow down, workers have families that want them around.

UPDATED August 14, 2023

Mayor Castelli and the Middleburg Heights City Council understand that maintaining our roads is a top priority.  The Middleburg Heights Department of Public Service and Director James Herron coordinates and manages the work with our City Engineer – Mackay Engineering and regional partners including Cuyahoga County, the Northeast Ohio Areawide Coordinating Agency (NOACA), and the Ohio Department of Transportation.

Listed below are the planned and funded 2023 Middleburg Heights Road Construction Projects.  This list is updated periodically as projects are approved and funded by Middleburg Heights City Council.

Cherokee Trail (Cul-de-sac to Saratoga Drive)

The project involves full depth pavement, curb and driveway apron removal.  The street and driveway aprons will be poured with concrete.

Project Update:  Project was awarded to Tri-Mor Corporation in 2022 and work started in early Spring 2023.  Project is completed.


Fairweather Drive (Sheldon Road to Big Creek Parkway)

Fairweather Drive will receive pavement planing with chip seal and asphalt overlay, concrete curb and section repairs.

Project Update:  Project was awarded by City Council to Chagrin Valley Paving, Inc. in 2022.  Project started in May 2023. Project is completed.


James Drive (Indian Creek to Trenton Trail)

James Drive was reconstructed by Chagrin Valley Paving, Inc. with full depth concrete in Fall 2022 and will receive and asphalt overlay in Spring 2023

Project Update:  Asphalt work was completed.


Winona Circle

Winona Circle received pavement profiling and concrete full depth repairs in Fall 2022.

Project Update:  Chagrin Valley Paving, Inc. has completed asphalt work.


Claremont Avenue (Elmdale Drive to Fairweather Drive)

Chagrin Valley Paving, Inc. was awarded the contract in 2022 and Claremont will receive pavement planing with asphalt overlay and concrete repairs.

Project Update:  Project is completed.


Shelburne Drive

The street will receive concrete curb and section repairs and an asphalt overlay.

Project Update:  Project was awarded by City Council and RMH Concrete and Foundations was awarded the bid.  Project will start in mid-September.


Pawnee Trail (Gerald Drive to James Drive)

The project includes concrete curb and section repairs and an asphalt overlay.

Project Update:  Project was awarded by City Council to RMH Concrete and Foundations and will begin in mid-September.


Bardbury Avenue

Project was awarded to Specialized Construction, Inc.  The street will receive concrete curb and section repairs and an asphalt overlay.

Project Update:  Project is completed.


General Pavement Services Contract

The City of Middleburg Heights awarded the contract to Crossroads Asphalt Recycling, Inc. in Spring 2023.


Fry Road (Bagley Road to Sheldon Road)

Crossroads Asphalt Recycling, Inc. repaved Fry Road and the project is completed.


Cranbrook Circle

Middleburg Heights Service Department will be doing concrete repairs and Crossroads will is providing the asphalt overlay work.