Indian Creek Relief Sewer

The Indian Creek Sanitary Relief Sewer Project has begun and is expected to continue through October, 2027.

Construction continues to progress on the Indian Creek Relief Sanitary Sewer Project. Current work includes:

  • Installation of 24-inch sanitary sewer pipe along Indian Creek.
  • Preparation for manhole installation at Boring Pit #1.
  • Concrete placement in Boring Pit #2 in preparation for upcoming boring operations.
  • Installation of sand in the annular space between the carrier and casing pipes from Saratoga to Lexington Green.
  • Sawcutting from MH 205 to Saratoga Trail to allow continued sewer installation.
  • Ongoing boring and casing pipe installation east of Saratoga.
  • Continued excavation and construction of the bore pits between Saratoga and Lexington Green.

The contractor is also continuing work on the underground sewer system, including the installation of 60-inch sewer pipe along Indian Creek. Underground structure construction, which began July 27, is continuing as the project moves forward.

Please check the website for weekly project updates.

Traffic Update

To safely accommodate construction, Indian Creek Drive will be restricted to one-way eastbound traffic between Baldwin Creek and Gerald Drive for portions of the project. Motorists are encouraged to use caution when traveling through the area, allow extra travel time, and follow all posted traffic control signs.

The City appreciates the patience and cooperation of residents as this vital infrastructure project moves forward. Regular updates will be provided as construction progresses.

Banner for Indian Creek Drive Sanitary Relief Sewer project; includes 'Community Project Update' and 'Reducing basement sewer backups for our neighborhoods'.

Click to download presentation

INDIAN CREEK SEWER PROJECT TIMELINE

  • Project commenced 7/13/26
  • Tree removal commenced 7/13/26 will continue through 8/3/26
  • Equipment staging and mobilization 7/13 – 7/23
  • Bore pit excavation (Between Saratoga and Lexington Green) begins 7/23
  • Boring operations continue
  • Underground structure construction begins on 7/27
  • The contractor is working to shore up Boring Pit #2
  • They are continuing to install 60”  along Indian Creek
  • The boring contractor is working to Bore and install casing pipe from Saratoga east