Southland Smith Road Transformation
Work continues on the Southland Streetscape Project.
As of the end of September, the following work has been completed on Smith Road Streetscaping:
- Underground utilities have been replaced.
- Pavement replacement with reduced lanes and additional parking, new curbs, and drive aprons were installed.
- Decorative crosswalks, sidewalks, pavers, curb ramps, and median islands are 90% complete.
- The shared-use path on the northeast side of Smith Road was paved.
- Landscaping including ornamental trees, plantings, and irrigation were added.
- Traffic signal upgrades are 90% complete. Pedestrian crossings have been installed.
- Street lighting and gateway signs are 75% complete.