Construction Notice: Sheldon Road Resurfacing project will start August 19th, 2019

The Cities of BROOK PARK and MIDDLEBURG HEIGHTS Sheldon Road Resurfacing project will start August 19th, 2019 (weather permitting). Karvo Companies, Inc. will perform construction through the estimated completion date of October 25th, 2019.

The project will consist of pavement planning, resurfacing and concrete repairs on Sheldon Road.

Construction will be performed in three main phases:

Phase 1. Work will include pavement planing, pavement repairs, chip seal, and an intermediate asphalt course.

Phase 2. Work will include concrete work, not limited to curbs, casting adjustments and aprons, as necessary.

Phase 3. Work will include the placement of the asphalt surface course and final Pavement Markings.

PLEASE USE CAUTION when driving through the work areas.

The work will be performed Monday through Friday unless inclement weather forces the contractor to work on a Saturday.

If you have questions during normal working hours, please do not hesitate to call Rick Halishak of Mackay Engineering & Surveying (440)829-8897 or Karvo Companies, Inc. at (330) 929-9616.

We would like to thank you in advance for your patience during construction. The City of Brookpark, Middleburg Heights and Karvo Companies, Inc will do everything possible to minimize the inconvenience caused by this construction.